|
FREEPORT NEWS |
||
FREEPORT LIGHTS ON THROUGH HISTORIC BLACKOUT(Freeport,
New York August 18, 2003) - Lights were quickly restored during the
largest blackout in history thanks to the Village-owned and operated
electric utility and self-generating capacity at its two power plants.
Using all available generating resources in the Village, the
Freeport-owned electric utility was able substantially to meet the
electric needs of its customers throughout the two-day crisis. Within
eight minutes of the blackout, the utility had restored partial electric
service with operation of its first generating unit. Two hours and
thirty-eight minutes later, Freeport Electric was generating 40 MW of
electricity from all available generating units at Power Plants 1 and 2.
At the time of the blackout, Freeport Electric was supplying a typical
weekday summer afternoon peak of 54 MW through a combination of importing
both hydroelectric power from the New York Power Authority (NYPA) and
other market sources, and 8 MW generated at Power Plant 1. The blackout
severed all connections to imported power and interrupted service from the
operating Power Plant 1. Freeport
directed the first power generated to essential public services to
maintain public health and safety, including police operations, traffic
control, water supply, and sewage management. Throughout the crisis, the
Village Electric Department stayed in close and constant communications
with the Mayor's office, the Village Police and Fire Departments,
Department of Public Works and members of the Village Emergency Management
Team. This effort not only ensured that critical electric resources were
directed as needed to protect Village-wide public health and safety, but
also to high priority customers with extraordinary health or life support
equipment needs. Following
normal usage patterns, demand for electricity dropped through the evening,
and by 12:30 am Friday morning, Freeport Electric was fully meeting the
Village's energy demand. Beginning at approximately 8:00 am on Friday, as
daily activities picked-up and businesses began routine operations,
Freeport Electric continued to deliver essential service to its 15,000
commercial and residential customers. As the Village was capable of
providing 40 MW compared to a typically summer weekday peak of 50-60 MW,
users were advised to limit their electric use. Residents and businesses
were requested to limit use to strictly necessary appliances such as
refrigerators and lights and to disconnect items that draw a large amount
of electricity including air conditioners, computers, televisions and
other high use items until full power could be restored. In
order to maintain a consistent and reliable level of service until the
Village could restore its interconnection with the LIPA distribution
system, the utility implemented scheduled and controlled rolling
blackouts. During these periods, portions of the Village would lose
electric service for a one-hour period. When power was restored that area
was assured of a minimum of two hours of service, though typically service
continued for four-five hours. This process continued as needed into
Friday night until connection with LIPA was restored at 1:00 am Saturday
morning. "There
was an admirable level of cooperation and communication between the all
the Village Departments," stated Mayor William Glacken. "This
cooperation made Freeport a safe and comfortable haven in the vast sea of
darkness around us. If Freeport did not have its own generating units, it
would have remained dark until 1:00 am on Saturday when the LIPA service
was restored to our area". "More so," added Mayor Glacken,
"this outage highlights the critical importance of our Power Plant 2
generation project. Once the new dual fuel turbine generation project is
constructed and passes environmental and acceptance testing, and the old
Power Plant 2 diesels are decommissioned, Freeport will have enough
generating capacity to meet this summer peak demand without support from
the LIPA distribution system and out of Village sources. The need for both
the Village turbine and the proposed merchant project to be co-located at
Power Plant 2 to serve the LIPA region has never been clearer." Hubert
Bianco, Superintendent of Electric Utilities commended the working staff
of Freeport Electric. "Immediately, our operators and line crews
returned to the utility to help where needed. It is a time consuming and
meticulous process to bring all the generating units on line and to
reestablish electric service. These hardworking men and women worked
through the night, some for as much as thirty hours to serve their
community, neighbors, families and friends." After power was restored
to neighborhoods, line crews continued to service individual homes
experiencing service difficulties. |