Freeport Channel Crossing Electrical Improvement

Update: Notice of roadwork and temporary incidental road and driveway access restrictions on Ray St, South Main St. and surrounding streets; Hanse Ave and vicinity.

Traffic Plan Drawing - 2.20


Update: Traffic will be affected on Monday January 14th 2019 Through Friday, January 18th 2019 due to construction.

Traffic Plan - Clean 1-7-19

Update: Traffic will be affected on Monday January 7th, 2019 Through Friday, January 11th 2019 due to construction.

Update: Traffic Patterns will be affected Friday, January 4th, 2019 as well as Monday, January 7th 2019

Traffic Plan

Update: The initial stages of the Channel Crossing project has begun as of December 6th, 2018. Please see all alerts and uploads. Thank you.

Complete Project

The project will replace existing feeders and tie lines originally installed below the channel in 1967, through the
installation of new conduits installed using directional drilling or micro-tunneling. The improvements also include
removal of two riser poles and extending the underwater tie lines inland on the western side of the channel
through the right-of-way where they currently emerge to the intersection of Ray Street and South End Place.
Four new riser poles will be installed at Ray Street/South End Place and Ray Street/Bedell Street to diversify exit
locations.

Channel Crossing 1A